  <dc:title xmlns:dc="http://purl.org/dc/elements/1.1/">2016, EGS, Lincs, Geophysical Survey</dc:title>
  <dc:type xmlns:dc="http://purl.org/dc/elements/1.1/">series</dc:type>
  <dc:identifier xmlns:dc="http://purl.org/dc/elements/1.1/">https://portal.medin.org.uk/portal/start.php?tpc=015_bd82cd8e-cfd3-4a14-a737-5181c40f6c6b</dc:identifier>
  <dc:description xmlns:dc="http://purl.org/dc/elements/1.1/">EGS International Ltd (EGSi) were contracted by Centrica Renewable Energy Limited (CREL) to
undertake the 2016 post-construction (year 4) hydrographic and geophysical survey of the
Lincs OWF. These works were conducted as part of a wider post-construction monitoring
operation which included survey works on the adjacent L and ID windfarm.
Survey works on the Lincs OWF were predominantly carried out using the vessel EGS Pioneer.
Vessel mobilisation commenced on 18th August and were completed on 22nd August 2016;
this period included vessel downtime on 19th &#x2013; 21st August which caused a delay in the
mobilisation. Survey operations on board the EGS Pioneer were carried out between 22nd
August and 3rd September 2016 with the demobilisation taking place later on the same day. 
Following the main survey the Wessex Explorer was mobilised to survey a
potential UXO target in close proximity to LS19.</dc:description>